| The John F. Kennedy Center for the Arts - Washington, DC | ||||||||||||
| Two New 3-story reinforced concrete parking structures, East and West plaza Renovations, Tunnel Reconstruction, Complete Site Developme | ||||||||||||
| Scope of Services: Provide full-service Construction Materials Testing Inspection and Enviromental Engineering Services including: | Type of construction: Multi-level parking structure
Total Project Cost: $50,000,000
Duration of Construction: Complete fall of 2003
|
|||||||||||
| Deep Foundations Soil Reinforcment
Post-tension Inspection
Concrete
Masonry
Precast
Structural Steel Laboratory Services and Fied Testing Enviromental Testing Included: Water and Soil Testing Air Monitoring |
||||||||||||
![]() |
![]() |
|||||||||||